For this week's assignment we are supposed to evaluate the project's plan and talk about time management.
The Idea:
My idea for the final project is to make a fabbable CNC mill for PCBs at a low cost (less than 100€).
Project plan:
I plan to assemble the structure and test the movements manually before 31 of may. By 7th of June I plane to have at least 2 axes working perfectly. before th 14th of June I plane to be done with evrything and at least test the machine once as whole.
Schedule:
I plan to assemble the structure and test the movements manually before 31 of may. By 7th of June I plane to have at least 2 axes working perfectly. before th 14th of June I plane to be done with evrything and at least test the machine once as whole.
Here is the timetable for the tasks I used Agantty to make a gantt chart and finally I exported it as .csv file