Project Documentation
Project Proposal
Project Planning
Project Documentation
The Build Processes, Testing and Results
Final Project Presentation
Progress Milestones
25 to 30 May
- 25 May - Consulted local our Local instructors on my final project
- 25-26 May - Project Timeline Planning
- 26 May
- Decide on what materials I need and created a Bill of Materials (BOM) for the electronics, mechanical components and accesories required
- Collected electronic components from our local instructor
- 26-30 May - Answered questions for Exercise 17
- 26May - 30May - PCB Milling machine was out of service. Unable to mill any PCB; as the some tracks of were milled away..
- 26 May
- Went on to stuff in my backup Fabkit 4.0 board just in case the CNC2020 mill is not able to be repaired in time
30 May to 3 June
- 30 May - 1 June
- Study and review of how are the control circuitry going to be.
- Worked on EAGLE on the control circuitry
- 30th May - Troubleshoot and tried settle the Fabkt 4.0 board which was not functioning properly; SCK rc=-1 issue.
- 31st May - Partially fixed the 328p Fabkits 4.0 board and decided to to milled out the controller board for my Laptop Stand; after our local instructor had informed that the CNC2020 mill had been restore and working well on 30 th May afternoon.
31 May to 9 June
- 2 June - Stuff my ATtiny 85 controller board.
- 2 - 6 June
- Worked on the programming of my ATiny85 board.
- Connected my AC fan and my DC LED strip to the my thermistor board and successfully tested the both the NTC sensor function as well as manual control ON/OFF function of light and fan separately
- 7-8 June
- Further explored on how to code in the arduino programming when both the thermistor sensing and manual on/off programmes were combined into final control programme.
9 June to 15 June
- 9 June
- Working on the integration of all the components on my laptop stand.
- Design and fitting of housing for circuitry board.
- Laser cut the housing for the circuitry board
- 10 June
- Testing of circuitry and programmed function after integrated into the circuit holder prototype
- Testing of programmed functions as a whole.
- 12-13 June
- Assembly of all parts together
- Documentation of project
13 to 15 June
- Documentation of project and update of webpage
- Design of presentation.png page
- Putting a video together of final project
19 June
- Presentation of final project to Neil at random scheduled timing.
20 June - 28 June
- Refine website and documentation according to course requirements
Project Timeline