Week 19
Project Development
In this week I have to document the track
of development of project and the progresses,remaining things to complete etc.
Firstly I planned the development and
completing of project, and it is already explained in the week
17.
As per the project and its implementing,
following things are to be considered:
Availability of items,components,Tools and
resources, Proper working condition of machines,Programing and developing
design and Making the mechanical stuffs,Assembling and Final testing.
Main learing Outcomes
which I could get from this project and its implimentation will be beneficial
to me.
Firstly I
made a plan and then I can keep this plan there by implementing it as
per the plan.
As my project is a good concept and
presently there is no product in the market. As I explained earlierThe project is an inflatable coin bank, which increase in size the
more you insert coins in. A value would be attached to the bank opening door so
that it deflates the bank when its opened.
This will be a good as a product for
peoples and as well as for Kids.Which can create a saving mentality in
them through a funny thing.
I can finfd the resources and Also schedule
the work as per the availability of resources and components.
Some of the components may not be available
locally .Especially being a small country which is also a consumer based
nation.
Main things I have to consider
·
What is the dead
line?How much time I have left?
·
What tasks have been
completed,and what tasks remain?
·
How will I complete
theremaining tasks in time?
·
What has worked?
·
What hasn’t?
·
What questions still
ned to be resolved?
I have already planned the idea of completing the project as:-
1- Electronic design and production 2 Days (07/06/2017)
2- Programming and Testing of sensors.
3- 3D design and
printing 2 days(11/06/2017)
4- Assembling ,fixing
and Improvements 1 Day max (13/06/2017)
But as per the Information which we have received,Our
presentation will be on 16 th. So I should complete the things before that.Even
Friday is public holiday in kuwait,we should present on that day .So completing
all these things before it will be a good effort.
I already completed the Electronic design
and the Programming part earlier than I expected.
Since I am using the same board which I used
in Input week helped me to get extra time..
The 3D designing will be a problem .As I checked,
I have to design many things for me. The valve,T shape connector and the
container box etc.
Iyou can see the details which I documented
in final project documentation.
I am thinking about new application for 3D
design so that I could get more exposure in designing applications.
But the problem was I was unable to utilise
the complete 2 days of 3D designing which I planned.It was due to some personal
things.
So it took more than 3 days to finish these
designs and there by my next thing (Assembling and testing got delya.
As the 3D designs neeed to print and this
could take the time.I have to prit some parts may be twice to achieve complete
level what I am expecting.
So by considering these things I have to
neglet some rest and relaxing time from my routine to achieve this.
I have to find extra time from this. Especially
I should find much time for the documentation as welll
As there is a requirement of poster and as
well as the Presentation I need to find the time for that aswell. A big
question remaining is even after doing
these things and completing,Will my project will be a successful prototype or
not.
By the grace of almighty,I have a confident
that I could achieve this .