Week 19

Project Development

 


What is the Deadline? How much time do you have left?

The Deadline for my final project s  12/06/2017. I have only 4 days left to complete my project.


What tasks have been completed, what tasks remain?

  1. 1)Wooden Structure frame                completed 

➢2 days max ❬ 6/06/2017❭  

  1. 2)Electronic part                                completed 

➢2 days max ❬ 9/06/2017 ❭ 

  1. 3)Assemble all modules                on going 

➢1 day max ❬10/06/2017 ❭    

  1. 4)Fixing errors                                on going 

➢2 day max ❬12/06/2017 ❭   



How will you complete the remaining tasks in time?

Everything is moving soothly as per my plan and I have 4 days time in between my presentation time and the died line that I scheduled(presenttion time is 16/06/2017).  



What has worked?. 

• Microcontroller board & sensors  - (working)
Wooden Structure frame designing and assembling  - (working)


What hasn't worked?
Type of shutter is still under testing (metal for stronger protection or fabric for light weight)





What questions still need to be resolved? 

Which part of my frame is the best to place the board with sensors ?

Is it better to have metal shutter or clothe sheet shutter ?

 

 

TO FINAL PROJECT ->>>>>>>>

 

 

 