Time
what is the deadline? How much time do I have left?:
My project is due for friday the 16th of June, this is coming fast and still have a lot to do before being able to present something interesting.
I have approximatively one week left to be ready for presentation. I will have to manage the time really adequatly to achieve the goals I set for my project in time.
what tasks have been completed, and what tasks remain?
Task completed:
- Developping concept idea
- BOM
- Aquiring material needed
- Design Cad of the machine
- Slide design
Task remaining
- Assembling the machine
- CNC custom parts
- develop processing application interface to transform sound into draw
- prototype the software integration to the machine
- test/test/test
- system integration of the final build
- Documentation on the go.
How will I complete the remaining tasks in time?
To be able to complete the remaining task in time, I will need a lot of organisation and time managment,
I also plan my project development in a Spyral form, like Neil suggest us. The first build will be the two-axes machine that will be able to read G-code.
Then, only after that I will work on the box containing the mic and the process to transform waveform into a draw. It's a lot to do in a week so I really want to be able to
show something even if it's not totally done for the final presentation.
I Also use Trello and my google calendar to organize my time and my workflow. Here's is an exemple of what it looks like: