Period of Time
29.5. -19.6.
PROJECT MON 29.09. TUE WED THU FRI SAT/SUN MON 05.06. TUE2 WED2 THU2 FRI2 SAT/SUN2 MON 12.06. TUE3 WED3 THU3 FRI3 SAT/SUN3 MON 19.06. MO15 MO16 MO17 MO18 MO19 MO20 MO21 MO22 MO23 MO24 MO25 MO26 MO27 MO28 MO29 MO30 MO31 MO32 MO33
Clear Balance and walking Clear Balance           Getting walking                        
Product Def product definition
 Technical Solutions   technical solutions        
Principles of Walking principles of walking    
Mechanical Tests mechanical tests    
PCB Development pcb development        
Requierements for pcb requierements for pcb      
Software Developemt  developing pieces  of software    
Check Fisability check fisability    
Design Adjustment design adjustments pcb and body    
Production production          
Software Definition software definition  
Getting rid of Problems gettign rid of problems  
Assembling assembling  
Software adjustments software adjustment
Final Test Final Test